The Saint-Léger plant is located in the municipality of Saint-Léger in the Charente region. Its installed capacity amounts to 10.8 MWp and the electricity produced is connected to the local EDF distribution grid.
PV Modules: 46,020 Canadian Solar, Yingli (multicristaline c-Si). Inverters : SMA. Technology: Fixed Tilt. Ground mounted. Annual Avoided Emissions : 6,733 Metric Tons CO2. Household Supply: 4,234 homes.
PPA System : 20-year PPA under French FiT (Tariff Order March 2011). System size : 10.8 MWp. Start construction date : July 2011. Commissioning date : October 2011. EPC Contractor : TSK. O&M Provider : TSK. Land: 23.5 Hectares.